PPDS PDS priorities

hi experts,

Is it possible to set ppds pds priorities?

The scenario is as follows.

I have 2 PDS with operations and reources as follows -

PDS - 1 PDS - 2

0010 A 0010 B

0020 C 0020 C

All A,B and C are finitely planned.

The requirement is -

If PDS - 1 is not available (due to resource 'A' cap 100 utilized), system should select PDS - 2 to meet the delivery date. (in PPDS production planning run using heuristics (without quota arrangement) )

As per my knowledge, system will create delayed planned orders with PDS -1



Helpful Answer