on 05-20-2011 6:44 PM
hi experts,
i am using sap ecc6 ehp4 ready db2 9.1 fp9 on hp-ux 11.31
i am installtion sap on cluster we have 2 node.
in node1 i installed the ASCS sucsessfully now i m installtion database instance everything goes file but at the 34 phase
Running phase: Alter Tables Volatile. its taking time its runing from 4 Hr, its my first time
is it genral or there is some problem
kindly suggest
thanks
sadiq
Hi Experts
any one has suggetion please guide?
thanks
Hi experts
Running phase: Alter Tables Volatile is solved now i stuck in the
Running phase: Create Temporary License ..its running from last 10 Hrs.
Kindly suggest.
thanks
Edited by: sadiq iqbal on May 24, 2011 11:24 AM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
10 | |
9 | |
8 | |
6 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.