what is the priority of Contracts

Former Member
0 Kudos

hi,

Can anyone let me know the answer to the following query;

If for a material , I have a centrally agreed contract for the material group, a value contract for the material and plant.

which one would the system select during automatic source determination???

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Centrally agreed contract for a material group or material? If you have created centrally agreed contract for a material and a value contract for material and plant system will take centrally agreed contract as priority.

If its a material group this means you have created without material master and its account assigned? In that case it will take contract created for material and plant.

Infact you can simulate your self and check how the system is bheaving.

Regards

Sangeeta