on 05-20-2011 12:36 PM
Hello Everyone,
We have a issue with CTS+ in our project. Transport is running from solman to production portal and its running since very long time for some 6 hours. Anyone have any idea to solve this problem
Thanks & Regards,
Ravi
Hello Mr,
Have your basis administrator checked system load?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi there,
System load and all is fine. Problem is its deploying all the DC's of the ESS component, instead of the one which has been modified. Its deploying the standard dc's of other countries which are not used in our environment too. Its running since some 4 days and not ended yet. It has deployed some half number of dc's of total count and expecting it may run for another 3-4 days. Can anyone help how to make CTS to deploy only the changed dc instead of all the other one's.
Thanks & Regards,
Ravi
User | Count |
---|---|
95 | |
11 | |
10 | |
9 | |
9 | |
7 | |
6 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.