Dear All,

I would like to know how system is allow capturing of scrap in time ticket confirmation though total yield is confirmed.

Case-

Order created- I have production order number say 1000001 having 3 operations and total quantity of order is 100. There is no planning scrap in order.

confirmation -i have confirmed first and second operation as total yield for 100 each. After confirming total yield quantity of 100 for first operation, if i have enter again 10 quantity as a scrap for first operation, system is allowing to do so.

Query - Is this a standard behaviour of the system?, how system is allowing though i have confirmed total quantity of yield for the first operation.

Plz suggest how to control if total quantity is confirmed system should not allow to enter surplus quantity in scrap field of time ticket confirmation.