Creating/Copying a Work Centre,also a Production Scheduler and Cost Centre.

Former Member
0 Kudos

Hi All,

I am trying to create a new work centre based on the settings of a previous one? First of all,how I can do this?

Secondly,after I have created the new work centre (having copied being copied from another),I need to create a new production Scheduler and Cost Centre? How I will be able to do so,also?Will the Production Scheduller and Cost Centre assignments fom the old work centre be copied,too,or I will need to create/copy these from scratch?

All help greatly appreciated,will award points to all useful answers.

PAPJ1.

Edited by: PAPJ1 on May 20, 2011 11:01 AM

Accepted Solutions (1)

Accepted Solutions (1)

former_member186193
Active Contributor

Hello,

You can create a new work center by copying an existing work center. in the cr01 screen in the copy from column put the plant name and Ref. work center name and put enter. all the existing data will be copied to the newly created work center. no need to create new assignment to Production Scheduller and Cost Center.

Hope it helps.

Regards

Alok

Former Member
0 Kudos

Thanks Alok,will proceed as you advised,have awarded points.

PAPJ1.

Answers (1)

Answers (1)

Former Member
0 Kudos

Have created this as requested.