Network 4004391 requires assignment to an activity number

pradeep_mahamuni
Contributor
0 Kudos

Hi

I have created PR in PS WBS > Network > Internal Activity > by assignininh material to this Internal activity. While doing this system took to me on settlement rule credation screen for the activity.

Previously it was not system was not taking me to this screen.

Can any body tell me why ?

I alredy maintained settlment profile for the network type having defaule settlment to WBS. And now system status of activity is CRTD SETC SETM

PR created succesfully.

Now when converting PR into PO i am getting folowing error message.

Network 4004391 requires assignment to an activity number.

Message no. KI292

Diagnosis

The given network cannot be assigned without specifying an activity number.

Procedure

Enter the number of the network activity required.

please reply ASAP.

regards,

Pradeep

Accepted Solutions (0)

Answers (3)

Answers (3)

pradeep_mahamuni
Contributor
0 Kudos

There was co validation active from FI-CO side which is placing the cost object WBS. by which systrem was giving the error as system is finding the mismatch between network WBS and PO WBS

Former Member
0 Kudos

Hello Pradeep,

Could you please explain how did you solve this problem? how did you find the CO Validation?

Best regards

Jose Marin

former_member230675
Active Contributor
0 Kudos

Are you creating any manual reservation for network?

Are you using PSM?

Is the PO for a subcontracting?

The error is depend on the above factors.

******

Please refer the below notes..

373525

419902

552598

not sure whether the above notes are relevant for you, (hope it helps)

virendra_pal
Active Contributor
0 Kudos

You need to use account assignment category F

Check your configuration for requisition document type

pradeep_mahamuni
Contributor
0 Kudos

Hi Viren,

As i am creating PR from PS my a/c assignment category is Q and config for doc type is fine.

I am facing this issue only in QUALITY system, in develoment and production system all is working fine.

Even though settlement profile is attached to network type why system is taking me to settlement rule cteation screen while creating activity ? As i alredy maintained settlement profile then settlement rule shuld be created automatically and system should not take me to that scrren.

And for the PO i am taking reference of the created PR so alredy theres is reference of a/c assignment WBS > Network > acitivity as it is created through PS.

As i said i am facing this issue only in QA and not DEV and PROD i am not able to identify the reason.

regards,

pradeep_mahamuni
Contributor
0 Kudos

Hi,

Please update

regards

Former Member
0 Kudos

Try again with a new project. If you still face the issue raise an OSS to SAP.