on 05-20-2011 9:43 AM
Dear all
Is it possible to execute a similar report as IMCCP3 - Transfer Plan to Project Budget based on a range of WBS Elements. Can a new report be created to allow this. The standard transaction only allows this based on Project.
Thank you
PRG
yes, you could always create Z tcode as you required.
Please make a functional spec and discuss with your abaper.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.