on 05-19-2011 4:16 PM
Dear PM Guru's,
while assigning the Components to the Operation in Task list creation , one Information message populated and along with that one new screen also populated Create Standard BOM: Initial screen. why its populating ? what i have to do ? i never seen such a like this problem. please help me how to overcome this information and screen? is there any specific reason ? why system populates this one ? in Back ground is there any Customization problem? i am not understanding this one. Maximum i am trying to findout the issue but i am not complete that one. please help me in this scenario
thanks
Prajal
Hi
When ever you assign any free component in task list (other then BOM) system create a internal BOM in background, thats why you are getting a new screen while assigning.
So to avoid this you have to do some config settign for BOM, Please follow the path and assign the default value for BOM.
Plant Maintenance and Customer Service---Master Data in Plant Maintenance and Customer Service-Bills of Material- Define Default Values
here define all entries may be in your case entries are not mainteined here.
Please check and confirm.
Shail
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Can you specify the information populated during assignment of components to operation
regards
thyagarajan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.