on 05-19-2011 3:57 PM
Experts,
Is any way for confirming milestones rathe than putting the dates manually in the milestone ?( I have invoicing plans attached to these milestones).
Thanks
psconsultant
If you have milestones attached to the WBS you have to enter the dates manually. If they are attached to an activity the milestones will be triggered when the activity is confirmed.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
My scenario is invoicing plan.
One external activty with five milestone attached to it. I cannot confirm the activity as this will pass the actual dates to all milestones and that will remove all invoicing block.
each milestone represent leach line item in invoicing plan. have to contro the date individually
Bro,
In standard system if you maintain milestones at activity level you can have only one event of trigger that is confirmation of activity. The moment you confirm the activity all the milestone will be triggerd and block will be removed. there is no concept of confirming the milestone so you need to remove the billing blok manually in sales order.
Regards
Abhishek Sinha
User | Count |
---|---|
85 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.