MRP generated schedule lines


I made a scheduling agreement say "YYY" with material "A". The target quantity specified is 100. I had made all the relevent settings & MRP is generating schedule lines successfully.

But the schedule lines generated for material "A" for the SA "YYY" are more than the target quantiy 100.

I want to know if I can restrict MRP to generate the schedule lines upto the sppecified target quntity only. How can I do that? Are there any settings for this?

If not then can anybody explain me what is the use of target quntity with respect to MRP?




Hi Manish 123,

You will only see warning as seen by the highlight in ME38 on the schedule lines created when MRP generated quantity exceeds the target quantity.