Dear experts,
I have the following flow: I'm creating a subcontracting order with a number of component in a BOM. I need an outbound delivery for each subcontracting order (and I'm likely to have multiple subcontracting orders per vendor per day), with a link in the delivery of both the FG (to be produced by the subcontractor) or at least the subcontracting PO. I've already looked at the ME2O transaction but this one seems to consolidate everything to one delivery per vendor, without a link to the PO.
An aditional requirement is that we need to be able to do a mass-creation of the deliveries,
Thanks in advance,
M
the delivery of components to a subcontractor has no relation to a subcontract order in core SAP.
Such feature is only possible with the new AD_SUBCON enhancement if I am not mistaken
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.