on 05-19-2011 6:03 AM
Hi friends
I have finished product around 2500.but i want run MRP for 100 materials only.how can i run MRP for particular materials and pl give me the t code for that.
Next time if i run MRP for 50 materials what will happen for reaming 50 materials plannig? it will chage or not?
Pl help me to find these things
Thanks
selva
Hi,
Refer this artical,
[ZTPP_MD03 Single level u2013 Multiple Item Functionality u2013 An Enhancement to MRP|http://www.sdn.sap.com/irj/scn/index?rid=/library/uuid/300fb0ef-93f5-2d10-7d8c-b758567ac5de]
Regards,
Dhaval
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Thanks for your reply
but i want run MRP for only 100 materials out of 2500.if i run MDBT or MD01 it will take all materials for planning.So how can i run MRP for those 100 materials only and how can input the demand data for 100 materials if i use md61it is very long process so how can i input forecast data pl guide me
Thanks
selva
Hi,
Are you trying with Reqmt plan option or using material radio button option? I think you are using material option so you are feeling it s time consuming.
Try with reqmts plan option in MD61 so you can maintain PIR & forecasting data for multiple materials together in single transaction with MD61 itself.
Alternately, you can try LSMW for the same exercise also if you feel MD61 steps are time consuming.
Hope this helps.
Regards,
Tejas
Hi,
I hope you are creating with refrence of material, in place of this just go eqmts plan wise & give plan with some logic like march2010 etc then enter here you can get screen like excel & can fill.
there no other short cut for md61, you can adopt SOP but not sure it suited to your buisness requirement or not.
Thanks.....Rakesh