Reg...MRP Run

Former Member
0 Kudos

Hi friends

I have finished product around 2500.but i want run MRP for 100 materials only.how can i run MRP for particular materials and pl give me the t code for that.

Next time if i run MRP for 50 materials what will happen for reaming 50 materials plannig? it will chage or not?

Pl help me to find these things

Thanks

selva

Accepted Solutions (1)

Accepted Solutions (1)

dhaval_choksi3
Active Contributor
0 Kudos

Hi,

Refer this artical,

[ZTPP_MD03 Single level u2013 Multiple Item Functionality u2013 An Enhancement to MRP|http://www.sdn.sap.com/irj/scn/index?rid=/library/uuid/300fb0ef-93f5-2d10-7d8c-b758567ac5de]

Regards,

Dhaval

Former Member
0 Kudos

Hi

Thanks for your reply

but i want run MRP for only 100 materials out of 2500.if i run MDBT or MD01 it will take all materials for planning.So how can i run MRP for those 100 materials only and how can input the demand data for 100 materials if i use md61it is very long process so how can i input forecast data pl guide me

Thanks

selva

dhaval_choksi3
Active Contributor
0 Kudos

Hi,

One more option will be club all those 100 materials under one mrp controller and then activate user exit M61X0001.

search in this forum and in google also if you need more help on this exit.After that run md01 using exit key and parameter.

Regadrs,

Dhaval

Former Member
0 Kudos

Hi,

You can make it with MRP area , activate MRP area & make group of 100 material under one MRP area & then run MRP on mrp area basic.

Thanks

Rakesh

Former Member
0 Kudos

Thanks for your answers

pl guide me how to enter forecast data for all materials? if i use MD61 it takes so much time

thanks

selva

Former Member
0 Kudos

Hi,

Are you trying with Reqmt plan option or using material radio button option? I think you are using material option so you are feeling it s time consuming.

Try with reqmts plan option in MD61 so you can maintain PIR & forecasting data for multiple materials together in single transaction with MD61 itself.

Alternately, you can try LSMW for the same exercise also if you feel MD61 steps are time consuming.

Hope this helps.

Regards,

Tejas

Former Member
0 Kudos

Hi

If your above problem resolve then just close the thread and give point for new issue create new thread.

Thanks

Best regards,

Nilesh i

Former Member
0 Kudos

Hi,

I hope you are creating with refrence of material, in place of this just go eqmts plan wise & give plan with some logic like march2010 etc then enter here you can get screen like excel & can fill.

there no other short cut for md61, you can adopt SOP but not sure it suited to your buisness requirement or not.

Thanks.....Rakesh

Former Member
0 Kudos

Thanks for your helpful answer i got some idea.

thanks

selva