GR based IV indicator changes


We are on SRM 5.0 SP12,ECS.

For material PO's ,the indicators GR_IND and IR_IND is not set and no follow on docs exist for the PO than GR_BASEDIV can be modified in SRM PO.

However if one of the indicators is set,can the GR_BASEDIV be changed in SRM PO?

Also for one of our PO's,when the IR_IND is set and if we try to change/uncheck the GR_BASEDIV in SRM PO,the changes are not replicated to ECC.When I manually run the FM for the PO transfer,the changes are than transported to ECC.

Can someone advise why the changes for the GR_BASEDIV are not replicated to ECC in the first attempt??