In MD04 i have aplanned order that is set to start on 5/27/11. Not all of the parts are in stock for the BOM to be built for the planned order. MRP runs in a batch file every night but it is not creating a PR for the some of the missing parts. Can someone give me some guidance as to why the PR is not being created. I have reviewed the raw material that the PR is not being created for against the other raw materials in the BOM that PRs have been created and the settings are the same for MRP.
Thanks in advance for help,
Sean
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Please check the for that material stock is available or existing PR or PO is available to meet the dependent requirement
if No
please check the planning file entry for that material in MD21
Is the planning file entry is checked for your material? then RUn MRP, system will create a procurement proposal to meet the dependent requirement
If not create in MD20
and run MRP system will create a Procurement proposal for your requirement.
If the MRP type of the material is VB-reorder point, then Run MDAB once, it will solve your problem
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
9 | |
9 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.