hi

how to inspect external process operation which are given for subcontracting, how to reject the operation which was done by subcontractiong

regards

Baswa

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member186193
Active Contributor
0 Kudos

Dear Raj,

Inspection of external process is done in the same way as of internal one.

Please check the following:

1. You must make sure that the operation control key in the production order specifies external processing.

2. You must activate a goods receipt inspection for the operations to be processed externally by:

a. Specifying an inspection type (inspection lot origin 01) in the routing (external processing data for the operation)

b. Activating this inspection type in the material master of the final product

Regards,

Alok Tiwari

madlercm
Active Contributor
0 Kudos

Just the same as an internal operation. You should have an in-process inspection.