hi
how to inspect external process operation which are given for subcontracting, how to reject the operation which was done by subcontractiong
regards
Baswa
Dear Raj,
Inspection of external process is done in the same way as of internal one.
Please check the following:
1. You must make sure that the operation control key in the production order specifies external processing.
2. You must activate a goods receipt inspection for the operations to be processed externally by:
a. Specifying an inspection type (inspection lot origin 01) in the routing (external processing data for the operation)
b. Activating this inspection type in the material master of the final product
Regards,
Alok Tiwari
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Just the same as an internal operation. You should have an in-process inspection.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.