One of my product having one operation in externel
Once it coming back after the externel operation confirmation is happening(here material number is not changing)
In this point i want to create a inspection lot on confirmation
how we can achieve this what is the inspection type we want to give
Give me a details step
Faisal
Hi Friend ,
Procedure for Quality inspection for external operation is :
1) Assign the operation in routing which is done external processing
control Key : PP02 ( External processing )
Click on indicator : Insp char. required.
Hence when production order is released for above scenario , double click on the operation and click on create PR.
Than PO from PR.
material is relaesed for external processing agianst PO .
when material is get external processing and come in through GR . Material goes to quality stock.
after quality ok , its come in unrestricted stock.
Regards
Vinod
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You can use the inspeciton lot origin 01 if a goods receipt is posted for an externally processed production operation.
You can store this inspection type in the respective operation of a routing.
Refer SAP help portal
http://help.sap.com/saphelp_erp60_sp/helpdata/en/2d/351a26448c11d189420000e829fbbd/content.htm
Regards
Luke
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You can use 04 origin or also explore 17.
In operation overview maintain/explore inspection type for external inspection
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
11 | |
10 | |
6 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.