hi Experts,
I'm newbie in SAP.
when I changed the numerator value in the material master, will it also be changed automatically in the numerator value in the PO that has been issued before the change date?
or it is also depend on the Price control condition in the PO.
if it's no control, so the numerator value will still the same since the PO is issued?
and if it's "GR date", will it be automatically updated (the numerator value) once there is goods receipt?
or the price control condition in the PO is only related with the condition price in the info record?
could you please adv
thanks
Andika
System does not make any changes to existing document. All the changes are applicable to documents created after changing material master etc...so in your case there will be no change on existing PO and corresponding Goods receipts.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
7 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.