cancel
Showing results for 
Search instead for 
Did you mean: 

Alternate units of measure in PR

Former Member
0 Kudos

Hi Everyone,

i've created a purchase requisition using pounds as the Base Unit of Measure on the Material Master Record. we purchase several chemicals in other units of measure, such as gallons or drums. Thus, we need to be able to purchase these chemicals using Alternative Units of Measure on the PR and PO, but we need to be able to receive for them in pounds to be consistent with our inventory since all of these will be issued out in pounds. I am aware that SAP allows the PO to be created in an Alternative Unit of Measure specified on the Material Master Record, but we need to have the requisition expressed in the Alternative Unit of Measure as well.

How can we do it?

Thanks in advance

Accepted Solutions (1)

Accepted Solutions (1)

amitbakshi3
Active Participant
0 Kudos

Hi,

The system picks up SKU (Stock Keeping Unit) which is Base UOM at Purchase Requisition. All Alternate UOMs maintained in Material Master will be picked up while Making a PO or performing a Goods Movement (GR/GI) where based upon your settings you can select the desired UOM while the system will still maintain by default value of Base UOM in SKU.

Hope it helps,

Best regards

Amit Bakshi

Answers (2)

Answers (2)

Former Member
0 Kudos

Thanks all....

JL23
Active Contributor
0 Kudos

PR is internal document, hence its quantity is expressed in the stock keeping unit, which is your base unit, and nothing else than the unit you internally use.

why do use a base unit which you do not want in your documents?