Schduling in Recipe

Dear All.

I want to check the schduling in Master Recipe C202 transaction for updating same in material master, i have maintained Machine time & Labour time in recipe then i try in recipe from menu bar RecipeSchdulingSchdule but not getting activity time for phase, start & finish time is 7:00 only. Same thing is happenning in Routing properly then why it is not working in Recipe?

I have maintained relationship between phases also.

Due to this after process order creation for all phases start & finish time is showing 7:00 only.

Please suggest how to resolve same.




See there is one big diffeent between work center/resource usage in routing and recipe.

When you used workcenter in routing then processing formula is used for capacity calculation while in the case of master recipe it is other formula/

so check in your work center whether you have maintain formula in other formala field or not.