Hi,
I have a problem with planning run to sales order. We have a configurable material which have make to order strategy. MRP Run does not create planned order to some of our sales order. I think it has relation with schedule lines but i can not understand the problem.
If schedule line has 1 as confirmed quantity MRP run can not plan but 0 as confirmed quantity MRP Run creates planned order. How can i solve this problem?
Regards,
techmastere
Hi,
Order for which qty is confirming, check which schedule line is determined and which requirement type system is determining.
then in VOV6 for schedule line tick mark availability check & Transfer of requirement
for requirement class OVZG tick mark availability check & Transfer of requirement
Note: if schedule line is not relevent for availability check & ToR then system always defaul confirm quantity.
kapil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.