Hi, I need to update fields: LRMDT, RZAEH and ADCONFTIME in table MHIS. Accidentally we technically completed some preventive orders.
We reset the Technically completed status in the orders, but the related plans were not updated in the Schedule call item tab.
Hi,
Completion date & time of the call objects are updated in MHIO table.
Whats the date in MHIS table Before TECO cancellation & after TECO cancellation?
[Use of MHIS & MHIO Tables|http://help.sap.com/saphelp_di471/helpdata/EN/a1/3bd5edf77811d4961300a0c93029cf/content.htm]
Even in MHIO table, once you do TECO, completion date will be updated. Even after TECO cancellation, that date will not get changed. After doing TECO again on some other date, new date will replace the old one.
Regards,
Maheswaran.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.