on 05-17-2011 5:43 PM
Hi Friends,
We are using same user status profile and project profile for two kind of projects ( differentiate based on scale field of WBS element).
If scale is A then follow the sequence ( 20>40>50-->60).
If scale is B then follow the sequence ( 20>30>50-->60).
As of now we can not achieve both functionality using same status profile, so by configuration we can achieve this using
one project profile/two status profiles/validation- substitution;
like if scale is A the use status profile ST1
If scale is B then use status profile ST2.
Any other pointers or that is the only way ( i explained above ) we can achieve that functionality.
REgards
Ashu
> As of now we can not achieve both functionality using same status profile, so by configuration we can achieve this using
> one project profile/two status profiles/validation- substitution;
>
>
I doubt validation / substitution is possible without a user exit.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
As far as i know what you have mentioned is the only way out because it may not be possible to maintain 2 different sequences for a single status profile. Using validation/substitution with respect to the scale you have mentioned seems to be a good way of maintaining the correct status profile for the relevant WBS.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi ,
I think only possible way is defining two project profile and using two status profiles .
As in our current business process the scale field comes from interface , workflow creates the project definition and first level WBS element till here it is not defined that what kind of project would be. after that interface create other project objects and assigns scale field to level 2 WBS elements.
Now status profile is assigned based on project profile, may I keep that field blank and later we can define that pice of code in intreface program that if scale is X then assign status profile ST1 and if Y then ST2.
I don't think validation/substituton will work here like
If project profile is # PD001
WBS scale is =X
then asign status profile as ST1.
Regards
Ashu
Hi,
Would it be possible to use only one status sequence ( 20>30>40>50>60), & define uper limits & lower limits accordingly.
If two different tems change user satus.you can limit acces to different levels using authorization keys efined to that particular level.
Hope this would open another point of view on this mater.
Regards,
SL
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.