PR Release date in TAB>Quantity/Dates

Hi Experts ,

When i am creating a PR then In the TAB>Quantity/Dates the release date is coming same as the delivery date .

As per my opinion it by default should be same as the PR requested date .and when it release by( me54 or me55) .then it will update as the dated on which we are releasing the PR.

Please Suggest

Varun Bisaria

Former Member
Former Member replied

Hi Varun,

The field 'release date' is a bit confusing. It has nothing to do with

the date you perform the release strategy (transaction ME54 or ME55).

The help on the field tells you more about it.

The release date does not mean PR release approval date.

In PR table/EBAN-FRGKZ or ME53 screen you can find the 'release date',

then press F1 -> purchase requisition release date which means for the

material to be available on the date it is needed the PR must be release

on xx.xx.xx (date) (that's requirement date less GR proessing time, GR

proessing time, planned delivery time, and purchasing department

processing time).

In ME53 screen -> item detail -> MRP data block (include release date.)

click 'statistics' icon -> administrative data (include release ind. and

rel. strategy).

In ME5A -> press F1 on 'release date' of initial screen which have same

explain for this field.

There is no actual PR release date field in EBAN, so in PR display,

we can not see "actual PR release date".

BR