Hi Experts ,

When i am creating a PR then In the TAB>Quantity/Dates the release date is coming same as the delivery date .

As per my opinion it by default should be same as the PR requested date .and when it release by( me54 or me55) .then it will update as the dated on which we are releasing the PR.

Please Suggest

Varun Bisaria

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Varun,

The field 'release date' is a bit confusing. It has nothing to do with

the date you perform the release strategy (transaction ME54 or ME55).

The help on the field tells you more about it.

The release date does not mean PR release approval date.

In PR table/EBAN-FRGKZ or ME53 screen you can find the 'release date',

then press F1 -> purchase requisition release date which means for the

material to be available on the date it is needed the PR must be release

on xx.xx.xx (date) (that's requirement date less GR proessing time, GR

proessing time, planned delivery time, and purchasing department

processing time).

In ME53 screen -> item detail -> MRP data block (include release date.)

click 'statistics' icon -> administrative data (include release ind. and

rel. strategy).

In ME5A -> press F1 on 'release date' of initial screen which have same

explain for this field.

There is no actual PR release date field in EBAN, so in PR display,

we can not see "actual PR release date".

BR

Nadia Orlandi

Former Member
0 Kudos

Dear,

Nadia Orlandi

Can I assign Pr release date in TAB>Quantity/Dates with actual PR release date . So that this date shows the date when PR release and not the date same as delivery date.

Thanks & Regards

Varun Bisaria

Answers (2)

Answers (2)

Former Member
0 Kudos

Please check purchsing processing time through Txn OPPQ(choose tab External Procurement).

pankaj_singh9
Active Contributor
0 Kudos

Hi,

Release Date = Requirement date less GR processing time, planned delivery time, and purchasing department processing time.