Copy WBS Plan to Plan -Network Costing not copyied

former_member213716
Participant
0 Kudos

Dear Expert,

I am using t-Code CJ9BS - Copy WBS Plan to Plan (Indiv.) to copy the project Plan from 0 version to 1 version. but it will not copyied..

were as if i will use the Manuall cost planning then it will copyied from 0 version to 1 version...

My problem is that i am using network costing but not able to copy the plan from 0 version to 1 version..

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

This message was moderated.

former_member230675
Active Contributor
0 Kudos

you did not read sap help properly..

you can not maintain network costing in version 1

former_member213716
Participant
0 Kudos

Dear Sir,,

I want to copy the version 0 plan in version 1 for reference as a backup..

might be i had not read the SAP help properly....

Thanks for your valuable suggestion ..i had got my solution...

i am just sharing the same...

As per SAP Note 71547

we can copy the Network Costing and Internal Order Costing in to other version also from version 0.

former_member203108
Active Contributor
0 Kudos

Dear, SAP Help clearly says which transaction to use to copy network costing also. That is why I said refer SAP Help.

@abdul

you can not maintain network costing in version 1

You can maintain network costing in version 1 i.e., version other than 0 as of EHP3.

former_member230675
Active Contributor
0 Kudos

rkp@sap is referring sap note 71547, which is talking about Releases 3.0/3.1

former_member203108
Active Contributor
0 Kudos

Refer SAP Help.