Process order settlement

Dear All,

We are into process industry.

Still we have not run settlement process. Every month we are doing TECO and DLV of all the process orders .

Now we are planning to run process order settlement process. For that I have run the KKS1 - variance calculation (Test run).

Now variance calculated for all the process order till date (which are TECO and DLV). We required to settle only those process order which are created

in new financial year i.e. after 1st April, 2011.

Because If variance is very high in old process order.

Thanks in advance,

Nirav

Former Member
replied

Hi

Error 1: Go to OKO7 - Allow Settlement receiver MAT in Settlement Profile 90... Or make a Copy of 90 as Z90 and allow MAT in it

Error 2: Go to OKO7and allow max no of dist rules as 999

Ignore the warning msg