on 05-17-2011 5:39 AM
Can anybody tell me the difference between the per unit price in the material master accounting view and the moving average price in the table MBEW-VERPR.
Because there is a difference in these values for all the materials in a plant.. Where comes the difference..
Karthick P
Hi Karthick,
There is surely difference between MAP & Price Unit fields in material master.
MAP indicates moving avg price for your material whereas price unit field means whatever MAP you've maintained is for how many units. e.g. say for example you've maintained MAP Rs 100 and it is price for 10 unit then you need to specify as 10 in price unit.
Hope this is the only thing you are looking for.
Regards,
Tejas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Karthik,
During production the cost of the material will be calculated either in MAP or standard price. Moving average price is not the actual price of the material. Let say, the raw material price is keep on varying every week. Eg. The price of ROH in Week 1 is Rs.100, W2 is 125 and W3 is 150. The price of the material in W1 will be Rs.100, W2 will be Rs.112.5 and in W3 it will be Rs.125.
If you take per unit price in W3, it will be Rs 150 where as MAP in W3 will be Rs.125.
Hope you understand.
Best Regards,
Umashankar
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.