on 05-16-2011 1:15 PM
Hi all,
In one of the substitution rule defined for WBS a routine exit U555 is used to substitute Plant from additional fields of Cost center master data. Now I have to see whether this routine exit is active. How can I see?
In OPSN i see that routine exit mentioned in Step but missing under the EXITS tab in Prerequisite. So can I be sure it is inactive. The other problem is this substitution should come into play whenever project will be created and then we save it. But here projects are automatically changing status to REL during creation itself and substitution is missing. Later when I am changing project status to TECO and then saving then substitution is carried on.
I need to fix all these things up for proper functioning so that the routine exit is active and substitution is carried on during Release of project. To stop automatic release of projects too.
clsoing
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi All,
Can you tell me though there is automatic substitution ticked in OPSA but substitution is not taking place during project creation and save. It takes place during the next status change and save.
We need to repair around 5000 projects. is there any way of mass substitution? So that the values are retrieved for plant field for 5000 projects at a time.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Abdul,
We have found a program which substitutes Plants in mass from CC master data. But when I am running the program it throws an error " Fill in all required fields" and cannot save the data. Even though substitution and valaidation is carried out.
When I go to project builder I find all mandatory fields filled up. Only one problem I face when I go to Depreciation Simulation Tab and click on Distribution button it says error "Both asset class and capitalization date are not maintained!
Message no. AO365 "
But my question is for normal save of project it works. Is it that during substitution it is reading the above tab or during project saving? How to come out of this?
So when I run the program it comes like this:
Factory calendar copied from plant
Substitution Project Definition carried out
Substitution WBS Elements carried out
Validation Project Definition carried out
Fill in all required entry fields
Data cannot be saved
I cannot find any mandatory fields to be filled up when I see in project builder.