Hello Everyone,
I have one requirement in my ongoing project.
I have created a Project "Construction of Road" and below this there are few WBS.
And in one of the WBS, i have Network and Activites mapped to it. The structure looks as shown below:
Construction of Road (Project Def)
GRANULAR SUB-BASE (WBS)
MATERIAL FROM CRUSHER (Activity)
LOADING COST (Activity)
TRANSPORTATION COST (Activity)
SPREADING WITH GRADER (Activity)
COMPACTION (ROLLER) (Activity)
In activities Spreading with Grader and Compaction i am using 2 machines Grader and Roller respectively in completing these activities.
How can i bring these machines into Project? Also i want to keep track of the following on the machine
STANDERD DIESEL CONSUMPTION PER HOUR
STANDERD DIESEL CONSUMPTION PER SHIFT
WORKING HOURS PER SHIFT
DIESEL CONSUMPTION PER SHIFT
DIFFERENCE IN DIESEL CONSUMPTION
PLANED OUT PUT PER SHIFT
OUTPUT ACHIEVED FOR SHIFT
DIFFERENCE IN OUTPUT
The above data i am able to capture by defining the machines Grader and Roller as equipment in SAP. But i am lost on how to map this machines on to may project "Construction of Road"
Can any one
Hi,
Simplest way is create these equipments are PRT and assign those PRT to these activities.
Since these are big machines it is not good to use PRT. Standard functionality is available in EC & O with ETM (equipment and Tools Management).
The work around is create these machines are work centers and also activity types for these machines to capture cost and maintain in the activity. create a functional location for each project and assign these equipments whenever you move these equipments to site / project.
hope it clears your doubt
thanks
abdul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Just for my understanding-lets say that Grader is created as a Work Center in SAP....after that we create 2 activity types in SAP,one for hour consumption and the other for diesel consumption.Then we maintain the rates in KP26 for the relevant Cost center.And we create the following 2 activities in the Project-
a) Per hour tracking
b) per shift tracking
For each of the activity,we maintain the standard diesel consumption in some place...lets say the User Field for quantity and the planned consumption in the Work field.
Now as we confirm the activity as the equipment is utilized then the actual consumption would be captured.
On the lines suggested by you,would this be the right way to proceed?
Thanks and Regards
Shekhar