Hi,

I have created a new Cost Component Structure and in this I have given three attributes:

1. Material Consumption

2. Activity

3. Over head

Ans assigned the proper cost element against all the above. Now when I am creating cost estimate for a material in this it is showing amount in Itemaziation under Category G (Overhead)

I want to know how the amount is populated in this category.

Please help me.

Thanks & Regards,

Vivek Srivastava

Accepted Solutions (1)

Accepted Solutions (1)

ajaycwa1981
Active Contributor
0 Kudos

Hi Vivek

These are the categories system uses for its own purpose and denotation

Mat Costs are denoted as M (if i am not wrong)

Ovh with G and Sub Con charges with L

It has been programmed that way

br, Ajay M

vivek_srivastava12
Active Contributor
0 Kudos

Hi Ajay,

Thank you so much for looking into my quey.

My query is little bit different. I want to know how system calculates the amount for over head when we create Cost Estimate.

Regards,

Vivek

ajaycwa1981
Active Contributor
0 Kudos

Hi

It depends on your costing sheet that you assigned in val variant

you need to do maintain overhead rate in KZM2 or KZS2

br, Ajay M