on 05-16-2011 7:09 AM
Hi Experts,
I am facing an issue regarding remote process chain variant, as i have added it in an existing process chain, Now its throwing an error in Quality and the changes are also not visible..Please help me out in finding a solution..
Regards
Arpita
After you have transported the process chain you need to manually activate the chain in order for the changes to reflect.
Rgds, Ghuru
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
One existing process chain is there, i have added a remote process chain variant, it executed successfully in development but when we transported that process chain to quality the changes that i made in DEV is not visible.
I have included that chain in a metachain as well so in production the whole metachain is failing because of this local chain.
And in Production the error is
The following error occurred during the remote function call for
destination SCD100
Hi,
The issue has not been resolved yet.Please help me out in this..only the variant for remote process is not visible in BW Quality system. where as the the process chain in APO system is successfully running in APO DEV System..
What could be the problem with the remote process variant. Please help me..
Regards
Arpita
Hi,
when i am transporting it to Quality or production system, that variant for remote process chain is not visible. I have tried it many times. Connectivity between the systems are fine.
I have kept APO System as destination
And Destination for callback BW System..
Please let me know if i am wrong..
Regards
Arpita
Edited by: Arpitac on May 25, 2011 8:51 AM