Service condition PRS minium value.

Former Member
0 Kudos

Hi,

I want to maintain in the service contract the following condition (PRS):

For a particular service rate is 10$ per meter but their is minimun quanty of 100 m.(1000 $) So even if we create a Service entry of 50 m the price should be 1000$.

How do I do this? The PO is created wrt to contract and than the Service entry sheet is created.

Thanks

Arun

Ii

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

In Service Condition Master against PRS condition maintain minimum and maximum value. By doing this, system will not allow amount to be exceeded/decreased in PO against PRS condition and will give error.

To do this first maintain PRS Service condition manually.

SAP Menu -> Logistics -> Material Management -> Service Master -> Service Conditions -> For vendor with (without) plant

Whichever is applicable.

I hope this helps.

Regards,

Ahmad Farhan Khalid