Hi,

We are using SRM 7 classic scenario.

Instead of supplier list we are using contracts with material group and dummy price maintained.

When creating a free-text for a product category where a contract exists the price entered manually in SC is overwritten by our dummy contract price. Is there a way to prevent that?

br

Anders

Edited by: Anders Öhrling on May 13, 2011 4:51 PM

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member183819
Active Contributor
0 Kudos

Hi

how many valid contracts available for the product category?

You need to trsin the requestioner department what is dummy contract and your requester depat should not assign this dummy contract.

You please inform the requestioner department what is the real use of dummy contract price.

Muthuraman

Former Member
0 Kudos

In Classic scenario it is standard that contract price gets defaulted in SC when a contract exists for the combination. You can use BBP_DOC_CHANGE_BADI to ignore contract price in the SC.

Thanks,