on 05-13-2011 2:56 PM
Hi Experts
I closed the Production orders in our Quality Box in error. Is there any way to set the Production orders back to TECO in MASS processing? In the Controlling Forum they gave me COHV with 250 (set/delete user status) but it didn't work. I have to do some more testing of variances and now I can't as all are closed.
Please help
Kind regards
Dawn
FI/CO
Hi Dawn,
U mean to say u closed all the orders using COHV or did u get any error during the execution of the T Code in this please explain what is the Error.. or if you would have closed the process order means done TECO then there is no standard T code in SAP to reverse the same in mass.. but individualy.
CO02/COR2 Enetr the order number.. in the header Process/production order --> Functions --> Restrict processing --> Revoke technical completion.
in case of closed same way Restrict procesing --> Revoke closing
Thanks & Regards,
Sampath
Edited by: sampath s on May 14, 2011 8:51 AM
Edited by: sampath s on May 14, 2011 8:51 AM
Edited by: sampath s on May 14, 2011 8:58 AM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.