unable to generate planned orders

Former Member
0 Kudos

Dear SAP guru,

tried to execute long term plan thru tcode MS01. However upon evaluation of MRP run result at MS04, the system was only able to generate independent requirements and 0 planned orders. why is this so?

Accepted Solutions (1)

Accepted Solutions (1)

former_member186193
Active Contributor
0 Kudos

Hello,

Pls check MRP type, strategy group and confirm if no stock is available.

Thanks

Alok

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi ,

Please check the current stock in the system, it may be happened that current stock in the system is more than the independent requirement , so system will not generating planned order.

Otherwise check the setting for MRP type , strategy group .

Regards

Vinod

madlercm
Active Contributor
0 Kudos

Bobby, something sounds wrong, since independent requirements are never generated by the system, but rather are the input to the planning process!

Former Member
0 Kudos

sir,

yes they are the input. what i meant was, that on ms04 you will only see independent requirements, and no planned orders. understand now?