We are planning to have SAP RFID. Once operational, do we need to send SAP Material Master field data to RFID? For ex; when the description of a material is changed, do we need to send this new information to RFID system through Idoc (or some other way)?

Regards

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Yes. This is available in SAP AII which is configurable. Material Idoc is the best way. Activate change pointers generally (Customizing for Logistics - General -> Supply Chain Planning Interfaces (SCPI) -> Auto-ID Backend Integration --> IDoc Processing --> Material Master Data IDocs -> Activate Change Pointers Generally).

Hope this helps.