on 05-12-2011 11:38 AM
Hi,
We are planning to have SAP RFID. Once operational, do we need to send SAP Material Master field data to RFID? For ex; when the description of a material is changed, do we need to send this new information to RFID system through Idoc (or some other way)?
Regards
Yes. This is available in SAP AII which is configurable. Material Idoc is the best way. Activate change pointers generally (Customizing for Logistics - General -> Supply Chain Planning Interfaces (SCPI) -> Auto-ID Backend Integration --> IDoc Processing --> Material Master Data IDocs -> Activate Change Pointers Generally).
Hope this helps.
Thanks,
Naveen