i have a situation where in one week the SNP planning run creates only one purchase requsition with single item for the requirement and in another it creates multiple purchase requisitions with single items...
iam unable to understand how the multiple purchase requisitions are created..can you share your ideas,
Thanks
Hi,
Check the Lot Sizing procedure defined in the product master.
It should be periodic lot size and period type is week and there should be some entries in the number of periods field.
Thanks,
'nandha
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI,
Yes offcource we can get multiple purchase req from SNP heuristics. here is some scenarios.
1) it depends on lot size settings in product master. in your case you may be getting multiple orders of fixed lot size since demand qty is more then that of fixed qty
2) if you maintained multilple sourcing( inbound quota arrangement) you will get multilple purchase req.
Check above settings carefully..
Regards
Thennarasu.M