CJ40 plan cost values not appearing in KKA2 screen

former_member806234
Participant
0 Kudos

HI Controllers,

I am configuring for Result analysis (POC). Here I need to plan for the WBS element, based on this I will calculate RA POC values.

Here my problem is I can see the values from Revenue planning (CJ42) but i can not see the values from CJ40 (Cost planning) to KKA2 screen.Pls help me how can i see the CJ40 values also in KKA2 result screen.

Thanks in advance

Regards

Sneha

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

In order to make the planned cost available in KKA2 for Result analysis run maintain Cost element planning by

CJR2 - Planning -> Costs in WBS -> Cost and Activity Inputs -> Change Here you need to maintain a Cost element from Cost and Revenue , In initial screen select Cost element 1 to 9999999999999 and execute it will take you to Cost element where you can plan the Cost and Revenue which will update the KKA2 .

Please try above and let me know the result.

Rgs,

Asim