Manufacturing Lead time, milestone operation wise

Good Evening to All !

I have a scenario. I am explaining this scenario through 1 example.

We have a material 'X'. Inhouse production time for this material is 6 days, which is maintained in MRP2 view.

Now in Routing of this material 'X' there are total 10 operations starts from 1 to 10. Operation No. '4' & Operation No. '10' are milestone operation. The workcenter for both milestone operations are different. Now in house production time which I maintained in material master is total lead time for material 'X'.

The requirement is: Workcenter of Operation "4 "wants to know on daily basis that what quantity should be delivered from their workcenter.

Now my question is that can I maintain this lead time(6 days) in 2 parts as:

Till operation "4" my lead time is 5 days &

From operation "5" to Operation 10 lead time is 1 day.

Please suggest all possible solutions.

Can APO help in this scenario.

Thanks in Advance.