Dear All,
We want to use internal order in the palce of Production order as PP is not implemented.
Cost estimate can be craeted by KKPAN (cost estimate w/o qty structure).
Can any body help me as how actual actual activities can be confirmed, material issues will be happened and finally receipt of FG materails from production plant to warehouse etc? and advantages and disadvantages of using the internal oredr against the production oredr.
Regards
Su
Hi
To post Actual Activity Qty - use KB21N
For Goods Issues - MB1A - 261 Mvt Type
For GR, MB1a 101.. I am not sure if this will be allowed for an IO or not
Better use CO Production order instead of Plan IO
br, Ajay M
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Can any body respond on this please?
Regards
Su
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.