cancel
Showing results for 
Search instead for 
Did you mean: 

Open Commitment

Former Member
0 Kudos

Hi PS Gurus,

In CJI5 I can see an open amount of A inches tied to purchase requisition .That requisition was converted to PO. The purchase order line and purchase req both show complete at B inches.

I ran RKACOR04 Program in SE38 also. Still itu2019s same.

Please help.

MM

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi PS gurus,

can i run this RKANBU01 in Se38

Please help

Thanks

MM

Former Member
0 Kudos

Yes. Run CJEN after this and check.

Former Member
0 Kudos

hi Gokul,

You mean to say that run RKANBU01 and then CJEN.

Thanks

MM

Former Member
0 Kudos

Yes

Former Member
0 Kudos

hI GOKUL,

thanks for the reply.

when i went to the RKANBU01 in SE38 , it said that transfer PReq & PO's. Where do they get transf'd.

Do we have any SAP note for this kind.

Many thanks

MM

Former Member
0 Kudos

Check this note,

Note 534993 - Short instructions RKANBU01

Former Member
0 Kudos

Hi,

To add, even after running the program, commitments may not be shown correctly some times.

If you are running on EHP4, then you have notes available for incorrect service pr / po commitments.

check the closed indicator in the pr item manually & cross check.

regards

Former Member
0 Kudos

Thanks

Issue got solved

Former Member
0 Kudos

Solved