Posting of PR/PO with Commitment Item and Fund Center


While I am preparing and posting normal Purchase Requisition (PR) with Budget on Commitment Item and Fund Center it has no problem but after posting the PR if I change the Cost Element and/or Cost Center then the changed is not impacted in the Budget.

Can anybody help me in this regard?

There should be some config where SAP should give impact on the change of Cost Element and/or Cost Center.




Hi, you mean that if you change CO-object in me52n there are no any changes for FM objects? (and FM object should derive from CO-object?)

Please check you derivation- tcode FMDERIVE, option for target field Overwrite with new value. Also try to trace derivation during saving(in me52n), is it triggers?