on 05-11-2011 8:01 AM
Hi ,
We have a requirement to copy the cost price VPRS from PGI - Accounting document to the Billing
I explored some configuration in copy controls by putting the Price source as E which will copy the cost price from the PGI to the Billing
But i found that it will do only when the Material price control in the Material master is V and not for S ( not sure there may be other settings also)
The scenario is , Order will be created ( lets say) in May and the dellivery is done in June
Mean while at the end of May the cost price will change only for the sales order in MR21 as Special sales order ( only for the order) and PGI is done in subsequent month
In the next month the price will effect the PGI and when i do the billing, the cost price is fetching from the Sales document and not from the PGI
Hope i am clear in explaining the requirement
Please let me know if there is any standard configuration available
regards,
santosh
Read OSS Note 547570 - FAQ: VPRS in pricing, this gives the details on how VPRS is working.
Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
If I am correct, VPRS in billing document will be copied from sale order only irrespective of price control. Right now, I dont have access to SAP and hence, unable to test. Will test and update later
thanks
G. Lakshmipathi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Hi in copy control delivery to billing at item level
Maintain PRICING TYPE - N (Transfer pricing components unchanged, NEW COST)
kapil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.