on 05-11-2011 7:37 AM
Hello.
I have following problem.
During goods receipt from process order (movement type 101) inspection lot is created automatically. When I display inspection lot data (transaction QA03) I see u201CData for AccAssgnmntu201D view. On this view I see u201CAccount assignment objectsu201D. I canu2019t find in the system configuration in which I could change assignment from Order to Cost center.
How can I change this assignment?
Regards,
Bogdan
Hi Bogdan,
1. It depends on the account assignment category that you use while creating purchase order.
2. If you use F you need to assign QM order and appropriate GL account.
3. If you use K you need to assign cost center.
Where exactly and with which logic you want to capture the cost of inspection?
Regards,
Anand Rao
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI Anand!
It not concerns purchase order. It concern proces order (created transaction COR1).
For this material is set InspectionType = 04 - Goods receipt inspection from production.
When the production is finished we use MIGO_GO transaction for this process order and movement type 101.
After that event inspection lot is created with assigned this process order as Account assignment object.
I am looking for configuration where I can change account assignment object to cost center.
Regards,
Bogdan