Hi All

The background job has created so many delivery schedules in future in the PO for a single PR with different delivery dates.

Is it background job is using some logic to throw the delivery schedules??? Or

Is there any way to restrict the delivery schedules to minimum in the PO??

thanks in advance

MSK

Accepted Solutions (0)

Answers (1)

Answers (1)

raghavan_iyengar3
Active Participant
0 Kudos

This could be because of Un-firmed PR's

When a background job runs MRP, and you have option to generate schedule lines through MRP, You need to be careful in PR's getting Firmed.

Suppose if a PR Gets firmed today morning, a new reqirement comes in the afternoon, another batch job runs in the evening, and firming indicator in PR gets changed and PR is unfirmed. hence a new schedule line will be generated for same PR.

While running MRP, please make sure you do not re process already processed MRP outputs like PR's S' Lines.

Raghavan