on 05-10-2011 7:58 PM
Hello EAM Experts,
We are running ECC 6.0. We would like to create a batch job for CO99, but are having the most unfortunate luck with finding ANY SAP documentation on this transaction.
Specifically we need to know the program criteria that is used to determine whether an order can be set to status CLSD as well as how to set up the batch job and error file output.
I've looked through the forum, wiki and the SAP document library without much luck. Anyone with links to SAP published content?
Kind Regards,
Leslee
hi
Can you clarify further.
When you run CO99 system will pick the order based the residence time specified according to when the TECO has been done. you can schedule the job is background with required frequency with the corresponding program SAPLKO99
regards
thyagarajan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Thyagarajan
Thank you for your response. I am looking for documentation that states clearly what the criteria, system parameters, or logic is that CO99 is programed and or configured for to do an automatic business close.
For instance is the logic : if work order system status = TECO and ZERO balance then system status is changed to CLS
I cannot find any SAP documentation on this t-code that explains its designed functionality. Application help takes the user to this document which does not spell out the purpose of the transaction, it just states ambigous CO functionality for lifecycle management of internal orders.
http://help.sap.com/saphelp_erp60/helpdata/EN/a9/ab7376414111d182b10000e829fbfe/frameset.htm
Any links to SAP documentation is very appreciated.
Kind Regards,
Leslee
Hi,
The limited documentation for collective close is here (it just gives a menu path to CO99):
http://help.sap.com/saphelp_erp60_sp/helpdata/en/5b/ae48624b8611d182ba0000e829fbfe/frameset.htm
The prerequisits to close are much the same as for closing a single order:
http://help.sap.com/saphelp_erp60_sp/helpdata/en/5b/ae48624b8611d182ba0000e829fbfe/frameset.htm
Specifically in the case of a collective close:
- Can be run for specific order type and plant based on retention time
- Only orders which do not have open items are closed.
- Order must have status TECO
To run in batch mode - Create a variant for program RKKBABS0 and schedule this as a job.
-Paul
Hi
Use program ''RKKBABS0" to close the order if you want to use your own criteria you can create a zprogram with help of this and can be used for closing the orders.
Shail
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
85 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.