Query on Labor Confirmation

Hi Seniors - I am having a query on labor confirmation in maintenance order.

When we enter the operation, the system calculate the value in DURATION FIELD based on time you enter in WORK FIELD and the no. of people we schedule for the said operation in NUMBER FIELD .e.g.

WORK = 4 HRS.

NO. OF PEOPLE = 2

DURATION = 2 HRS.

Now when planned cost is caluculated, it will be based on DURATION i.e 2 hrs. and while confirming the labor, we will put ACTUAL WORK as 4 hrs. so the cost will be calculated based on 4 hrs. and there would be a deviation of 2 hrs in PLANNED COST AND ACTUAL COST.

Please clarify.

Thanks & Regards

Manmohan K. Bajaj