on 05-10-2011 3:23 PM
Hi
i have a work order ,in this how the costs are calculated with the given material as well as components.when these costs are calculated. i mean at what stage they arecalculated in a order point of view.
can any one give clear explanation tof these?
Thanks in advance
divya nayana
Hi,
Once the order is released basing on the activity mentioned in the work cneter and the material selected would be considered as planned cost.Once activity confirmation is over it is being updated in actual cost and for material after migo it is being appered in actual cost.
Regards,
Sudhakar.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
The cost will be calculated automatically when you save or release the order according the valuation variant assigned to the order in IMG settings
regards
thyagarajan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.