Hi

a) How I can execute Mix cost estimate for all materials.

b) I have maintained the procurement alternate in Ck91n and maintained ratios in CK94. If I do not want to use mix costing then how this can be done as normal setting.

regards

Accepted Solutions (1)

Accepted Solutions (1)

ajaycwa1981
Active Contributor
0 Kudos

Hi Imdad

Q1 - You need to create a Proc Alt & Mix Ratio for all materials

Then execute CK11N and CK40N

Q2 - You need to remove the Mixing ratios and delete the Proc Alternatives....

Then it will be a normal costing using the 1st available Prod Version

br, Ajay M