Setup activity and resource utilization

Former Member
0 Kudos

Dear SAP Experts,

We are planning with setup activities determined via a setup matrix and the planned resource has an utilization # from 100%. Both planned activities considers the resource utilization to determine the activity duration. Is it possible to configure the system in a way that only production activity considers the resource utilization and the setup activity considers 100% utilization?

Example: We have a resource which the utilization if set to 65%, a setup transition of 390 minutes generates the setup activity with 600 minutes because of the resource utilization.

Appreciate any idea.

Thanks and BR

Mauricio

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Dear SAP Experts,

I could find a report that allow us to control if we want to use resource utilization or not in the setup activity.

Thanks and BR

Mauricio

Former Member
0 Kudos

Sorry, forgot to mention the report, the report is the /SAPAPO/TSTREAM_EFF_CHANGE

Thanks and BR

Andre